A fire-stopping survey examines the places where pipes, cables, ducts, joints and construction details pass through or interrupt fire-resisting walls and floors. Its purpose is to identify breaches, unsuitable installations and missing evidence, then provide a clear basis for risk-prioritised remedial work.
For building owners, responsible persons, principal contractors and facilities teams, a good survey is much more useful than a list of red marks on a plan. It should explain what was inspected, what could not be accessed, why a detail is defective and what information is needed before it is repaired.
Why fire stopping is needed
Compartment walls and floors are intended to resist the spread of fire and smoke for a defined period. Building services inevitably create openings through those barriers. Unless each opening is protected with an appropriate tested system, fire and smoke may travel into adjoining compartments, voids or escape routes.
In England, Approved Document B gives statutory guidance supporting the Building Regulations. It describes the need for compartment walls and floors to form a complete barrier and for openings for services to be appropriately fire-stopped. Existing occupied buildings must also be managed under the applicable fire safety legislation and fire risk assessment.
When should you commission a fire-stopping survey?
A survey is particularly valuable when:
- you have acquired a building with incomplete passive-fire records;
- a fire risk assessment or intrusive compartmentation survey identifies concerns;
- refurbishment, cabling, mechanical works or tenant alterations have affected fire compartments;
- you need to define the scope and cost of remedial works;
- quality assurance is required during a new installation programme; or
- previous repairs used unknown products or lack photographs and traceable installation records.
There is no single survey format that suits every building. The scope should reflect the building’s construction, use, occupancy, fire strategy, known risks and the level of assurance required.
What does a fire-stopping survey include?
Review of available information
The surveyor should first review relevant drawings, fire strategy information, compartment plans, product records and previous reports. This helps identify intended fire-resistance periods and separates a visible finish from a detail that can actually be verified.
Inspection of accessible compartment lines
The physical inspection typically covers accessible service risers, corridors, plant areas, ceiling voids, wall and floor penetrations, linear joints and interfaces with fire-resisting construction. Depending on the scope, opening-up or access equipment may be needed. Any limitations should be stated—not hidden in small print.
Assessment of each penetration
A competent assessment considers the wall or floor construction, aperture size, service type, insulation, movement, orientation and required performance. Fire-stopping products are tested as systems. Red sealant around a cable is not automatically compliant simply because it looks tidy.
Photographic and location records
Every finding should be traceable to a real location, ideally through marked-up plans or an asset register. Clear before-and-after photographs are essential for future maintenance and handover.
Risk-prioritised recommendations
Reports should distinguish urgent risks from routine improvement work and avoid treating every observation as identical. Prioritisation should take account of the compartment’s role, escape routes, occupancy and the extent of the breach, alongside the building’s fire risk assessment.
Common defects found during surveys
- unsealed cables, pipes or trays passing through compartment walls;
- generic expanding foam or mastic used without a suitable tested detail;
- plastic pipes without the correct collar or wrap;
- oversized apertures and unsupported seals;
- new services routed through an older fire-stopping system;
- damaged or incomplete coated-batt systems;
- services packed too closely for the proposed product system;
- unprotected linear gaps and wall-to-soffit junctions;
- poor labelling, missing photographs and no installation traceability; and
- a mismatch between the installed system and the wall or floor construction.
What should a useful survey report contain?
Before appointing a surveyor, agree the deliverables. A practical report should include the survey scope, reference information, access limitations, location and photograph of each finding, description of the defect, risk or priority, and recommended next action. Where a repair detail cannot be confirmed, the report should say what evidence or further investigation is required.
A quantified schedule makes tendering and programme planning easier. However, quantities alone are not a specification: the selected remedial system still has to be appropriate for the substrate, service configuration, aperture and required performance.
From survey to completed remedial works
- Validate the scope. Resolve access gaps, duplicates and unclear locations.
- Confirm specifications. Select tested systems appropriate to each configuration.
- Plan around the building. Coordinate shutdowns, permits, infection control, tenants and live services.
- Install and supervise. Use competent installers and follow the product-system requirements.
- Record the work. Capture before, during and after photographs, product details and locations.
- Quality-check and hand over. Close defects only after suitable review and provide usable building records.
Indigo Systems provides fire-stopping surveys, installation and remedial works across London and the South East. Our work is planned for real operating buildings, including commercial, healthcare, residential and public-sector environments.
Frequently asked questions
Is a fire-stopping survey the same as a fire risk assessment?
No. A fire risk assessment considers the overall fire risk and precautions. A fire-stopping or compartmentation survey is a more focused inspection of passive-fire barriers and the details that maintain them. The two should inform each other.
Will the survey be intrusive?
It can be. Some areas are visible, while others need ceiling access, panels or agreed opening-up. The scope should define the level of inspection and record inaccessible areas so nobody mistakes a sample survey for full coverage.
Can the surveyor also complete the repairs?
Yes, provided responsibilities, competence, specifications and quality assurance are clear. Some clients prefer separate survey and installation appointments; others value one accountable programme from discovery through to handover.
How long does a survey take?
That depends on building size, access, number of compartments, service density and required reporting detail. A site walkover can help establish a realistic scope before work begins.
Plan your fire-stopping survey
If you need to understand the condition of your compartmentation or turn an existing report into a deliverable repair programme, contact Indigo Systems with your building location, plans and known concerns.
Want to see this type of work in practice?
Browse Indigo project examples across healthcare, commercial, residential and public-sector buildings.
View Projects